Reference projects / Vertical-transmission wind turbineConditional feasibility

Reference project — read-only and public. Every number on these pages is computed live by the calculation engine from the stated design basis. Copy it into a project to change assumptions, resolve gaps and work with the agent.

Development plan

89 tasks, 610 engineering hours, 8 approval gates. Every task has a deliverable, inputs, method, dependencies, role, estimate and acceptance criterion; work stops at testable packages (spec §03). Critical path ≈ 19 working days if each task has one person.

S1 Concept intake → Concept brief and open-question register5 tasks · 22 h

Exit criteria: Function, environment, budget, scale and constraints captured · Source documents imported or listed as missing

TaskDiscipline / roleDeliverable and acceptanceDepends onhSchedule
S1-BRIEF
Concept brief and open-question register
Systems engineering
Systems engineer
Concept brief v1 with open-question register
✓ Brief states function, environment, scale, budget and constraints; every unknown is in the register
6
S1-G-01
Resolve G-01: Import the patent / design documents for the vertical transmission and the staged clutch arrangement.high
Systems engineering
Systems engineer
Answer recorded with its source, or an approved assumption
✓ Gap closed or reclassified with reason
S1-BRIEF4
S1-G-02
Resolve G-02: Is the rotor a vertical-axis rotor on top of the tower, or a horizontal-axis rotor with a right-angle gear into the vertical shaft?high
Aerodynamics and fluids
Aerodynamicist
Answer recorded with its source, or an approved assumption
✓ Gap closed or reclassified with reason
S1-BRIEF4
S1-G-05
Resolve G-05: How does the magnet control the centrifugal clutch (hold shoes retracted, add engagement force, or release a latch)? Are thresholds set by speed or by power?high
Mechanical / machine design
Mechanical engineer
Answer recorded with its source, or an approved assumption
✓ Gap closed or reclassified with reason
S1-BRIEF4
S1-G-08
Resolve G-08: Prototype budget and the funding target.high
Cost and funding
Project controls
Answer recorded with its source, or an approved assumption
✓ Gap closed or reclassified with reason
S1-BRIEF4
S2 Requirements and concept → Requirements baseline and selected concept2 tasks · 20 hgate

Exit criteria: Measurable performance targets · Jurisdiction, design life and safety requirements set · Alternative concepts compared

TaskDiscipline / roleDeliverable and acceptanceDepends onhSchedule
S2-REQ
Requirements baselineapprovalmedium
Systems engineering
Systems engineer
Requirements baseline (17 requirements) with measurable targets
✓ Every requirement measurable and verifiable; inventor approves
S1-BRIEF, S1-G-01, S1-G-02, S1-G-05 +18
S2-CONCEPTS
Alternative concepts and baselinesapprovalmedium
Systems engineering
Systems engineer
Concept comparison incl. conventional baselines; schematic diagrams
✓ Selected concept recorded with reasons
S2-REQ12
S3 Decomposition and plan → Approved development plan3 tasks · 41 hgate

Exit criteria: Every function mapped to a subsystem · Every part has discipline, analyses, standards and acceptance test · Dependency-ordered task graph approved

TaskDiscipline / roleDeliverable and acceptanceDepends onhSchedule
S3-DECOMP
System decomposition review
Systems engineering
Systems engineer
Product structure (48 items) with functions and interfaces
✓ No orphan function or requirement; every part has discipline, analyses, standards and acceptance test
S2-CONCEPTS8
S3-STANDARDS
Standards applicability matrix
Standards and compliance
Compliance engineer
Applicability matrix for 30 standards; acquisition tasks for missing documents
✓ Each standard: edition identified, acquired or purchase task raised, clauses mapped
S3-DECOMP30
S3-PLAN
Approve the development planapproval
Systems engineering
Project lead
Approved development plan and staffing
✓ Inventor / owner approves
S3-DECOMP, S3-STANDARDS3
S4 Preliminary engineering and sourcing → Traceable preliminary design and assumptions40 tasks · 314 h

Exit criteria: Load paths established · Candidate materials and commercial parts selected · Preliminary BOM

TaskDiscipline / roleDeliverable and acceptanceDepends onhSchedule
S4-DES-1.1
Preliminary design: Rotormedium
Aerodynamics and fluids
Aerodynamicist
Layout, load path, parametric CAD and assumptions list
✓ Load path closed; every part sized or sourced
S3-PLAN16
S4-DES-1.2
Preliminary design: Top bearing and rotor support
Mechanical / machine design
Mechanical engineer
Layout, load path, parametric CAD and assumptions list
✓ Load path closed; every part sized or sourced
S3-PLAN16
S4-DES-1.3
Preliminary design: Vertical transmission shaftmedium
Mechanical / machine design
Mechanical engineer
Layout, load path, parametric CAD and assumptions list
✓ Load path closed; every part sized or sourced
S3-PLAN16
S4-DES-1.4
Preliminary design: Ground-level gear stage
Mechanical / machine design
Mechanical engineer
Layout, load path, parametric CAD and assumptions list
✓ Load path closed; every part sized or sourced
S3-PLAN16
S4-DES-1.5
Preliminary design: Staged generator bankmedium
Electrical power
Electrical engineer
Layout, load path, parametric CAD and assumptions list
✓ Load path closed; every part sized or sourced
S3-PLAN16
S4-DES-1.6
Preliminary design: Braking and overspeed protectionmedium
Controls and software
Controls engineer
Layout, load path, parametric CAD and assumptions list
✓ Load path closed; every part sized or sourced
S3-PLAN16
S4-DES-1.7
Preliminary design: Power electronics, controls and electrical
Electrical power
Electrical engineer
Layout, load path, parametric CAD and assumptions list
✓ Load path closed; every part sized or sourced
S3-PLAN16
S4-DES-1.8
Preliminary design: Towermedium
Structural
Structural engineer
Layout, load path, parametric CAD and assumptions list
✓ Load path closed; every part sized or sourced
S3-PLAN16
S4-DES-1.9
Preliminary design: Foundationmedium
Civil and geotechnical
Civil / geotechnical engineer
Layout, load path, parametric CAD and assumptions list
✓ Load path closed; every part sized or sourced
S3-PLAN16
S4-DES-1.10
Preliminary design: Generator house, guards and service provisions
Manufacturing
Manufacturing engineer
Layout, load path, parametric CAD and assumptions list
✓ Load path closed; every part sized or sourced
S3-PLAN16
S4-PART-1.1.1
Detail: Blades (H-rotor, pultruded aerofoil)
Aerodynamics and fluids
Aerodynamicist
Part record: geometry envelope, material grade and condition, tolerances, process
✓ Blade static test to 1.35 × extreme load; mass and balance within tolerance
S4-DES-1.110
S4-PART-1.1.2
Detail: Blade struts / arms
Structural
Structural engineer
Part record: geometry envelope, material grade and condition, tolerances, process
✓ Fatigue check at 2P cyclic load; joint test
S4-DES-1.110
S4-SRC-1.1.4
Source: Blade and strut fasteners
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.13
S4-SRC-1.2.1
Source: Top radial bearing (spherical roller)
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.23
S4-SRC-1.2.2
Source: Thrust bearing carrying rotor and shaft weight
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.23
S4-PART-1.3.1
Detail: Shaft segments
Mechanical / machine design
Mechanical engineer
Part record: geometry envelope, material grade and condition, tolerances, process
✓ Fatigue reserve ≥ target; straightness ≤ 0.1 mm/m; balance G6.3
S4-DES-1.310
S4-SRC-1.3.2
Source: Segment couplings (disc type)
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.33
S4-SRC-1.3.3
Source: Intermediate steady bearings
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.33
S4-PART-1.3.4
Detail: Steady-bearing brackets in tower
Structural
Structural engineer
Part record: geometry envelope, material grade and condition, tolerances, process
✓ Bracket stiffness ≥ 10 × bearing radial stiffness requirement
S4-DES-1.310
S4-SRC-1.4.1
Source: Speed-up gearbox (planetary or helical)
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.43
S4-SRC-1.4.3
Source: Gearbox lubricant
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.43
S4-PART-1.5.1
Detail: Magnetically controlled centrifugal clutches
Mechanical / machine design
Mechanical engineer
Part record: geometry envelope, material grade and condition, tolerances, process
✓ Engages and releases at set thresholds with hysteresis; slip heat within plate rating at 30 engagements/h
S4-DES-1.510
S4-SRC-1.5.2
Source: Permanent-magnet generators 1.5 kW
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.53
S4-SRC-1.5.3
Source: Generator couplings (jaw)
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.53
S4-SRC-1.6.1
Source: Spring-applied fail-safe brake
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.63
S4-SRC-1.6.2
Source: Redundant overspeed sensing
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.63
S4-SRC-1.7.2
Source: Rectifiers, DC bus and listed hybrid inverter
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.73
S4-SRC-1.7.3
Source: Dump load / diversion resistor
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.73
S4-SRC-1.7.4
Source: Sensors: anemometer, shaft speed/torque, vibration, temperatures
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.73
S4-SRC-1.7.5
Source: Enclosures, disconnects, wiring and earthing
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.73
S4-SRC-1.8.2
Source: Tower base flange bolts (M24, class 10.9)
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.83
S4-PART-1.8.3
Detail: Tower base plate
Structural
Structural engineer
Part record: geometry envelope, material grade and condition, tolerances, process
✓ Plate bending and weld checks (AISC DG1)
S4-DES-1.810
S4-PART-1.9.1
Detail: Reinforced-concrete spread footing
Civil and geotechnical
Civil / geotechnical engineer
Part record: geometry envelope, material grade and condition, tolerances, process
✓ FS ≥ 1.5 overturning/sliding; bearing ≤ allowable from the geotechnical report
S4-DES-1.910
S4-SRC-1.9.2
Source: Reinforcement
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.93
S4-SRC-1.9.3
Source: Anchor rods (M30, F1554 Gr 55) and setting template
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.93
S4-SRC-1.9.4
Source: Base-plate grout
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.93
S4-SRC-1.9.5
Source: Earthing electrode and lightning protection
Sourcing and suppliers
Buyer
Candidate part numbers (≥ 2 makers), datasheets, price and lead time
✓ Ratings meet the sizing result with reserve; quote dated
S4-DES-1.93
S4-PART-1.10.2
Detail: Guards on rotating parts
Manufacturing
Manufacturing engineer
Part record: geometry envelope, material grade and condition, tolerances, process
✓ Interlocked access; ISO 13857 distances
S4-DES-1.1010
S4-PART-1.10.3
Detail: Lifting points and generator slide rails
Manufacturing
Manufacturing engineer
Part record: geometry envelope, material grade and condition, tolerances, process
✓ Generator swap demonstrated in ≤ 4 h
S4-DES-1.1010
S4-BOM
Preliminary BOM
Sourcing and suppliers
Buyer
Part-level BOM with make/buy, quantities, cost ranges and lead times
✓ Every part has quantity, make/buy and a cost range with its basis
S4-PART-1.1.1, S4-PART-1.1.2, S4-SRC-1.1.4, S4-SRC-1.2.1 +254
S5 Simulation and feasibility → Feasibility report and alternatives20 tasks · 106 hgate

Exit criteria: Energy balance closes · Mandatory criteria checked · Uncertainty quantified

TaskDiscipline / roleDeliverable and acceptanceDepends onhSchedule
S5-CALC-01
Rotor power, speed and torque at rated windhigh
agent runs CALC-01 →
Aerodynamics and fluids
Aerodynamicist
Wind rotor power, speed and torque — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.13
S5-CALC-02
Rotor power at the site mean wind (part load)high
agent runs CALC-02 →
Aerodynamics and fluids
Aerodynamicist
Wind rotor power, speed and torque — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.13
S5-CALC-03
Annual energy production at the sitehigh
agent runs CALC-03 →
Aerodynamics and fluids
Aerodynamicist
Annual energy production (Weibull site) — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.1, S5-CALC-013
S5-CALC-04
Staged generator bank at rated powerhigh
agent runs CALC-04 →
Mechanical / machine design
Mechanical engineer
Staged multi-generator drivetrain: energy balance — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.5, S5-CALC-013
S5-CALC-05
Staged generator bank at part load: staged vs one generatorhigh
agent runs CALC-05 →
Mechanical / machine design
Mechanical engineer
Staged multi-generator drivetrain: energy balance — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.5, S5-CALC-023
S5-CALC-06
Energy balance at rated: no output beyond inputhigh
agent runs CALC-06 →
Systems engineering
Systems engineer
Energy balance check — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.5, S5-CALC-01, S5-CALC-043
S5-CALC-07
Vertical shaft fatigue at rated torque with 2P ripple
agent runs CALC-07 →
Mechanical / machine design
Mechanical engineer
Shaft fatigue and yield (DE-Goodman) — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.3, S5-CALC-013
S5-CALC-08
Shaft critical speed with two steady bearings (3 spans)high
agent runs CALC-08 →
Mechanical / machine design
Mechanical engineer
Shaft first critical speed (uniform, simply supported span) — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.3, S5-CALC-013
S5-CALC-09
Rejected option: one 10 m span with no steady bearingshigh
agent runs CALC-09 →
Mechanical / machine design
Mechanical engineer
Shaft first critical speed (uniform, simply supported span) — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.3, S5-CALC-013
S5-CALC-10
Parked extreme wind on rotor and towerhigh
agent runs CALC-10 →
Structural
Structural engineer
Rotor and tower wind thrust, base reactions — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.8, S5-CALC-013
S5-CALC-11
Top bearing life (weight + operating radial load) and static safety at extreme wind
agent runs CALC-11 →
Mechanical / machine design
Mechanical engineer
Rolling bearing rating life (ISO 281 basic) and static safety — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.2, S5-CALC-01, S5-CALC-103
S5-CALC-12
Speed-up stage pinion bending (screening)
agent runs CALC-12 →
Mechanical / machine design
Mechanical engineer
Spur gear tooth bending (Lewis screening) — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.4, S5-CALC-013
S5-CALC-13
Clutch engagement onto a stationary generatorhigh
agent runs CALC-13 →
Mechanical / machine design
Mechanical engineer
Clutch engagement: torque, slip energy and temperature rise — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.5, S5-CALC-013
S5-CALC-14
Tower base flange bolts under parked extreme windhigh
agent runs CALC-14 →
Mechanical / machine design
Mechanical engineer
Bolted joint: preload, tightening torque, separation and slip — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.8, S5-CALC-103
S5-CALC-15
Spread footing: overturning, sliding, soil bearinghigh
agent runs CALC-15 →
Civil and geotechnical
Civil / geotechnical engineer
Square spread footing: overturning, sliding and soil bearing — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.9, S5-CALC-103
S5-CALC-16
Anchor rods: steel strength under factored extreme windhigh
agent runs CALC-16 →
Structural
Structural engineer
Anchor bolts on a bolt circle: tension and shear (steel strength) — result with checks and validity
✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated
S4-DES-1.9, S5-CALC-103
S5-LC-04
Simulate Emergency stop from overspeedmedium
Controls and software
Controls engineer
Time-domain or spectrum result with assumptions
✓ Brake applied at 1.3 × rated speed, generators disengaged
S3-PLAN16
S5-LC-06
Simulate Fatigue spectrummedium
Mechanical / machine design
Mechanical engineer
Time-domain or spectrum result with assumptions
✓ 20 years at the site distribution; 2P torque ripple on the shaft
S3-PLAN16
S5-LC-07
Simulate Loss of grid / load rejectionmedium
Controls and software
Controls engineer
Time-domain or spectrum result with assumptions
✓ Electrical load drops to zero at rated; dump load and brake respond
S3-PLAN16
S5-FEAS
Feasibility reportapprovalhigh
Systems engineering
Systems engineer
Feasibility verdict with best/base/worst cases, unknowns, validation plan and cost to resolve uncertainty
✓ Verdict traceable to results; independent review requested for safety-critical items
S5-CALC-01, S5-CALC-02, S5-CALC-03, S5-CALC-04 +1510
S6 Optimization and integration → Recommended configuration and trade study12 tasks · 53 hgate

Exit criteria: Interfaces compatible · Impacted calculations re-run

TaskDiscipline / roleDeliverable and acceptanceDepends onhSchedule
S6-I-01
Define interface I-01: Rotor hub to top shaft segment: torque, weight and rotor bending moment
Mechanical / machine design
Systems engineer
Interface control sheet: geometry, loads, fits, signals, ownership
✓ Both owners sign; dependent calculations re-run
S5-FEAS3
S6-I-02
Define interface I-02: Top bearing housing to tower top: radial rotor loads and weight into the tower
Mechanical / machine design
Systems engineer
Interface control sheet: geometry, loads, fits, signals, ownership
✓ Both owners sign; dependent calculations re-run
S5-FEAS3
S6-I-04
Define interface I-04: Steady bearings to tower brackets: radial support only
Mechanical / machine design
Systems engineer
Interface control sheet: geometry, loads, fits, signals, ownership
✓ Both owners sign; dependent calculations re-run
S5-FEAS3
S6-I-05
Define interface I-05: Shaft bottom to gearbox input (coupling, axial float allowance for thermal growth of the long shaft)
Mechanical / machine design
Systems engineer
Interface control sheet: geometry, loads, fits, signals, ownership
✓ Both owners sign; dependent calculations re-run
S5-FEAS3
S6-I-06
Define interface I-06: Power take-off to each clutch
Mechanical / machine design
Systems engineer
Interface control sheet: geometry, loads, fits, signals, ownership
✓ Both owners sign; dependent calculations re-run
S5-FEAS3
S6-I-08
Define interface I-08: Magnet driver command to each clutch; engagement state feedback
Controls and software
Systems engineer
Interface control sheet: geometry, loads, fits, signals, ownership
✓ Both owners sign; dependent calculations re-run
S5-FEAS3
S6-I-09
Define interface I-09: Generator AC to rectifiers / DC bus
Controls and software
Systems engineer
Interface control sheet: geometry, loads, fits, signals, ownership
✓ Both owners sign; dependent calculations re-run
S5-FEAS3
S6-I-10
Define interface I-10: Brake release / apply and overspeed trip
Controls and software
Systems engineer
Interface control sheet: geometry, loads, fits, signals, ownership
✓ Both owners sign; dependent calculations re-run
S5-FEAS3
S6-I-11
Define interface I-11: Base plate to anchor rods: tension, compression and shear
Mechanical / machine design
Systems engineer
Interface control sheet: geometry, loads, fits, signals, ownership
✓ Both owners sign; dependent calculations re-run
S5-FEAS3
S6-I-12
Define interface I-12: Footing to soil: bearing pressure, sliding resistance
Mechanical / machine design
Systems engineer
Interface control sheet: geometry, loads, fits, signals, ownership
✓ Both owners sign; dependent calculations re-run
S5-FEAS3
S6-I-13
Define interface I-13: Generator and gearbox heat rejected from the house
Mechanical / machine design
Systems engineer
Interface control sheet: geometry, loads, fits, signals, ownership
✓ Both owners sign; dependent calculations re-run
S5-FEAS3
S6-TRADE
Optimization trade studyapproval
Systems engineering
Systems engineer
Recommended configuration (mass, cost, energy, reliability) with Pareto comparison
✓ Mandatory constraints hold in the recommended configuration
S5-FEAS, S6-I-01, S6-I-02, S6-I-04 +820
S7 Costing and roadmap → Costed development plan3 tasks · 20 hgate

Exit criteria: NRE separated from unit cost · Partner scopes, schedule and funding milestones

TaskDiscipline / roleDeliverable and acceptanceDepends onhSchedule
S7-COST
Cost model
Cost and funding
Project controls
NRE vs recurring cost; prototype, pilot and production scenarios; contingency
✓ Quotes vs estimates labelled; currency, date, exclusions stated
S4-BOM, S6-TRADE8
S7-SCOPES
Partner scopes
Systems engineering
Project lead
Scopes of work for: Aerodynamics and fluids, Structural, Electrical power, Electronics / PCB (VX Design), Controls and software, Civil and geotechnical, Manufacturing
✓ Each scope lists inputs, deliverables, standards and sign-off
S6-TRADE6
S7-ROADMAP
Development roadmap and funding milestonesapproval
Cost and funding
Project lead
Schedule, budget per milestone, funding asks, contingencies
✓ Owner approves
S7-COST, S7-SCOPES6
S8 Handoff and later validation → Preliminary package, RFQs and test plan4 tasks · 34 hgate

Exit criteria: Drawings, models, calcs, BOM packaged · Specialist sign-offs listed · Not marked certified or construction-ready

TaskDiscipline / roleDeliverable and acceptanceDepends onhSchedule
S8-VXD
VX Design electronics handoff
Electronics / PCB (VX Design)
Systems engineer
Structured VX Design intake package
✓ VX Design accepts the intake without open questions
S6-TRADE4
S8-RFQ
RFQ packagesapproval
Sourcing and suppliers
Buyer
Drawings, specs, quantities, tolerances, inspection and delivery requirements per supplier
✓ Owner approves before any external disclosure
S7-COST8
S8-TESTPLAN
Prototype instrumentation and test plan
Test and validation
Test engineer
Test procedures for 8 requirements verified by test/inspection/demonstration
✓ Every test-verified requirement has a procedure and pass criterion
S6-TRADE16
S8-PACKAGE
Funding-ready preliminary packageapproval
Systems engineering
Project lead
Brief, requirements, structure, BOM, calcs, feasibility, risks, costs, roadmap — marked preliminary
✓ Reviewer approval status shown on every document
S7-ROADMAP, S8-RFQ, S8-TESTPLAN, S8-VXD6