Reference projects / Vertical-transmission wind turbineConditional feasibility
Reference project — read-only and public. Every number on these pages is computed live by the calculation engine from the stated design basis. Copy it into a project to change assumptions, resolve gaps and work with the agent.
Development plan
89 tasks, 610 engineering hours, 8 approval gates. Every task has a deliverable, inputs, method, dependencies, role, estimate and acceptance criterion; work stops at testable packages (spec §03). Critical path ≈ 19 working days if each task has one person.
S1 Concept intake → Concept brief and open-question register5 tasks · 22 h
Exit criteria: Function, environment, budget, scale and constraints captured · Source documents imported or listed as missing
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S1-BRIEF Concept brief and open-question register | Systems engineering Systems engineer | Concept brief v1 with open-question register ✓ Brief states function, environment, scale, budget and constraints; every unknown is in the register | 6 | ||
| S1-G-01 Resolve G-01: Import the patent / design documents for the vertical transmission and the staged clutch arrangement.high | Systems engineering Systems engineer | Answer recorded with its source, or an approved assumption ✓ Gap closed or reclassified with reason | S1-BRIEF | 4 | |
| S1-G-02 Resolve G-02: Is the rotor a vertical-axis rotor on top of the tower, or a horizontal-axis rotor with a right-angle gear into the vertical shaft?high | Aerodynamics and fluids Aerodynamicist | Answer recorded with its source, or an approved assumption ✓ Gap closed or reclassified with reason | S1-BRIEF | 4 | |
| S1-G-05 Resolve G-05: How does the magnet control the centrifugal clutch (hold shoes retracted, add engagement force, or release a latch)? Are thresholds set by speed or by power?high | Mechanical / machine design Mechanical engineer | Answer recorded with its source, or an approved assumption ✓ Gap closed or reclassified with reason | S1-BRIEF | 4 | |
| S1-G-08 Resolve G-08: Prototype budget and the funding target.high | Cost and funding Project controls | Answer recorded with its source, or an approved assumption ✓ Gap closed or reclassified with reason | S1-BRIEF | 4 |
S2 Requirements and concept → Requirements baseline and selected concept2 tasks · 20 hgate
Exit criteria: Measurable performance targets · Jurisdiction, design life and safety requirements set · Alternative concepts compared
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S2-REQ Requirements baselineapprovalmedium | Systems engineering Systems engineer | Requirements baseline (17 requirements) with measurable targets ✓ Every requirement measurable and verifiable; inventor approves | S1-BRIEF, S1-G-01, S1-G-02, S1-G-05 +1 | 8 | |
| S2-CONCEPTS Alternative concepts and baselinesapprovalmedium | Systems engineering Systems engineer | Concept comparison incl. conventional baselines; schematic diagrams ✓ Selected concept recorded with reasons | S2-REQ | 12 |
S3 Decomposition and plan → Approved development plan3 tasks · 41 hgate
Exit criteria: Every function mapped to a subsystem · Every part has discipline, analyses, standards and acceptance test · Dependency-ordered task graph approved
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S3-DECOMP System decomposition review | Systems engineering Systems engineer | Product structure (48 items) with functions and interfaces ✓ No orphan function or requirement; every part has discipline, analyses, standards and acceptance test | S2-CONCEPTS | 8 | |
| S3-STANDARDS Standards applicability matrix | Standards and compliance Compliance engineer | Applicability matrix for 30 standards; acquisition tasks for missing documents ✓ Each standard: edition identified, acquired or purchase task raised, clauses mapped | S3-DECOMP | 30 | |
| S3-PLAN Approve the development planapproval | Systems engineering Project lead | Approved development plan and staffing ✓ Inventor / owner approves | S3-DECOMP, S3-STANDARDS | 3 |
S4 Preliminary engineering and sourcing → Traceable preliminary design and assumptions40 tasks · 314 h
Exit criteria: Load paths established · Candidate materials and commercial parts selected · Preliminary BOM
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S4-DES-1.1 Preliminary design: Rotormedium | Aerodynamics and fluids Aerodynamicist | Layout, load path, parametric CAD and assumptions list ✓ Load path closed; every part sized or sourced | S3-PLAN | 16 | |
| S4-DES-1.2 Preliminary design: Top bearing and rotor support | Mechanical / machine design Mechanical engineer | Layout, load path, parametric CAD and assumptions list ✓ Load path closed; every part sized or sourced | S3-PLAN | 16 | |
| S4-DES-1.3 Preliminary design: Vertical transmission shaftmedium | Mechanical / machine design Mechanical engineer | Layout, load path, parametric CAD and assumptions list ✓ Load path closed; every part sized or sourced | S3-PLAN | 16 | |
| S4-DES-1.4 Preliminary design: Ground-level gear stage | Mechanical / machine design Mechanical engineer | Layout, load path, parametric CAD and assumptions list ✓ Load path closed; every part sized or sourced | S3-PLAN | 16 | |
| S4-DES-1.5 Preliminary design: Staged generator bankmedium | Electrical power Electrical engineer | Layout, load path, parametric CAD and assumptions list ✓ Load path closed; every part sized or sourced | S3-PLAN | 16 | |
| S4-DES-1.6 Preliminary design: Braking and overspeed protectionmedium | Controls and software Controls engineer | Layout, load path, parametric CAD and assumptions list ✓ Load path closed; every part sized or sourced | S3-PLAN | 16 | |
| S4-DES-1.7 Preliminary design: Power electronics, controls and electrical | Electrical power Electrical engineer | Layout, load path, parametric CAD and assumptions list ✓ Load path closed; every part sized or sourced | S3-PLAN | 16 | |
| S4-DES-1.8 Preliminary design: Towermedium | Structural Structural engineer | Layout, load path, parametric CAD and assumptions list ✓ Load path closed; every part sized or sourced | S3-PLAN | 16 | |
| S4-DES-1.9 Preliminary design: Foundationmedium | Civil and geotechnical Civil / geotechnical engineer | Layout, load path, parametric CAD and assumptions list ✓ Load path closed; every part sized or sourced | S3-PLAN | 16 | |
| S4-DES-1.10 Preliminary design: Generator house, guards and service provisions | Manufacturing Manufacturing engineer | Layout, load path, parametric CAD and assumptions list ✓ Load path closed; every part sized or sourced | S3-PLAN | 16 | |
| S4-PART-1.1.1 Detail: Blades (H-rotor, pultruded aerofoil) | Aerodynamics and fluids Aerodynamicist | Part record: geometry envelope, material grade and condition, tolerances, process ✓ Blade static test to 1.35 × extreme load; mass and balance within tolerance | S4-DES-1.1 | 10 | |
| S4-PART-1.1.2 Detail: Blade struts / arms | Structural Structural engineer | Part record: geometry envelope, material grade and condition, tolerances, process ✓ Fatigue check at 2P cyclic load; joint test | S4-DES-1.1 | 10 | |
| S4-SRC-1.1.4 Source: Blade and strut fasteners | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.1 | 3 | |
| S4-SRC-1.2.1 Source: Top radial bearing (spherical roller) | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.2 | 3 | |
| S4-SRC-1.2.2 Source: Thrust bearing carrying rotor and shaft weight | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.2 | 3 | |
| S4-PART-1.3.1 Detail: Shaft segments | Mechanical / machine design Mechanical engineer | Part record: geometry envelope, material grade and condition, tolerances, process ✓ Fatigue reserve ≥ target; straightness ≤ 0.1 mm/m; balance G6.3 | S4-DES-1.3 | 10 | |
| S4-SRC-1.3.2 Source: Segment couplings (disc type) | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.3 | 3 | |
| S4-SRC-1.3.3 Source: Intermediate steady bearings | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.3 | 3 | |
| S4-PART-1.3.4 Detail: Steady-bearing brackets in tower | Structural Structural engineer | Part record: geometry envelope, material grade and condition, tolerances, process ✓ Bracket stiffness ≥ 10 × bearing radial stiffness requirement | S4-DES-1.3 | 10 | |
| S4-SRC-1.4.1 Source: Speed-up gearbox (planetary or helical) | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.4 | 3 | |
| S4-SRC-1.4.3 Source: Gearbox lubricant | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.4 | 3 | |
| S4-PART-1.5.1 Detail: Magnetically controlled centrifugal clutches | Mechanical / machine design Mechanical engineer | Part record: geometry envelope, material grade and condition, tolerances, process ✓ Engages and releases at set thresholds with hysteresis; slip heat within plate rating at 30 engagements/h | S4-DES-1.5 | 10 | |
| S4-SRC-1.5.2 Source: Permanent-magnet generators 1.5 kW | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.5 | 3 | |
| S4-SRC-1.5.3 Source: Generator couplings (jaw) | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.5 | 3 | |
| S4-SRC-1.6.1 Source: Spring-applied fail-safe brake | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.6 | 3 | |
| S4-SRC-1.6.2 Source: Redundant overspeed sensing | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.6 | 3 | |
| S4-SRC-1.7.2 Source: Rectifiers, DC bus and listed hybrid inverter | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.7 | 3 | |
| S4-SRC-1.7.3 Source: Dump load / diversion resistor | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.7 | 3 | |
| S4-SRC-1.7.4 Source: Sensors: anemometer, shaft speed/torque, vibration, temperatures | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.7 | 3 | |
| S4-SRC-1.7.5 Source: Enclosures, disconnects, wiring and earthing | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.7 | 3 | |
| S4-SRC-1.8.2 Source: Tower base flange bolts (M24, class 10.9) | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.8 | 3 | |
| S4-PART-1.8.3 Detail: Tower base plate | Structural Structural engineer | Part record: geometry envelope, material grade and condition, tolerances, process ✓ Plate bending and weld checks (AISC DG1) | S4-DES-1.8 | 10 | |
| S4-PART-1.9.1 Detail: Reinforced-concrete spread footing | Civil and geotechnical Civil / geotechnical engineer | Part record: geometry envelope, material grade and condition, tolerances, process ✓ FS ≥ 1.5 overturning/sliding; bearing ≤ allowable from the geotechnical report | S4-DES-1.9 | 10 | |
| S4-SRC-1.9.2 Source: Reinforcement | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.9 | 3 | |
| S4-SRC-1.9.3 Source: Anchor rods (M30, F1554 Gr 55) and setting template | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.9 | 3 | |
| S4-SRC-1.9.4 Source: Base-plate grout | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.9 | 3 | |
| S4-SRC-1.9.5 Source: Earthing electrode and lightning protection | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.9 | 3 | |
| S4-PART-1.10.2 Detail: Guards on rotating parts | Manufacturing Manufacturing engineer | Part record: geometry envelope, material grade and condition, tolerances, process ✓ Interlocked access; ISO 13857 distances | S4-DES-1.10 | 10 | |
| S4-PART-1.10.3 Detail: Lifting points and generator slide rails | Manufacturing Manufacturing engineer | Part record: geometry envelope, material grade and condition, tolerances, process ✓ Generator swap demonstrated in ≤ 4 h | S4-DES-1.10 | 10 | |
| S4-BOM Preliminary BOM | Sourcing and suppliers Buyer | Part-level BOM with make/buy, quantities, cost ranges and lead times ✓ Every part has quantity, make/buy and a cost range with its basis | S4-PART-1.1.1, S4-PART-1.1.2, S4-SRC-1.1.4, S4-SRC-1.2.1 +25 | 4 |
S5 Simulation and feasibility → Feasibility report and alternatives20 tasks · 106 hgate
Exit criteria: Energy balance closes · Mandatory criteria checked · Uncertainty quantified
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S5-CALC-01 Rotor power, speed and torque at rated windhigh agent runs CALC-01 → | Aerodynamics and fluids Aerodynamicist | Wind rotor power, speed and torque — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.1 | 3 | |
| S5-CALC-02 Rotor power at the site mean wind (part load)high agent runs CALC-02 → | Aerodynamics and fluids Aerodynamicist | Wind rotor power, speed and torque — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.1 | 3 | |
| S5-CALC-03 Annual energy production at the sitehigh agent runs CALC-03 → | Aerodynamics and fluids Aerodynamicist | Annual energy production (Weibull site) — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.1, S5-CALC-01 | 3 | |
| S5-CALC-04 Staged generator bank at rated powerhigh agent runs CALC-04 → | Mechanical / machine design Mechanical engineer | Staged multi-generator drivetrain: energy balance — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.5, S5-CALC-01 | 3 | |
| S5-CALC-05 Staged generator bank at part load: staged vs one generatorhigh agent runs CALC-05 → | Mechanical / machine design Mechanical engineer | Staged multi-generator drivetrain: energy balance — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.5, S5-CALC-02 | 3 | |
| S5-CALC-06 Energy balance at rated: no output beyond inputhigh agent runs CALC-06 → | Systems engineering Systems engineer | Energy balance check — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.5, S5-CALC-01, S5-CALC-04 | 3 | |
| S5-CALC-07 Vertical shaft fatigue at rated torque with 2P ripple agent runs CALC-07 → | Mechanical / machine design Mechanical engineer | Shaft fatigue and yield (DE-Goodman) — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.3, S5-CALC-01 | 3 | |
| S5-CALC-08 Shaft critical speed with two steady bearings (3 spans)high agent runs CALC-08 → | Mechanical / machine design Mechanical engineer | Shaft first critical speed (uniform, simply supported span) — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.3, S5-CALC-01 | 3 | |
| S5-CALC-09 Rejected option: one 10 m span with no steady bearingshigh agent runs CALC-09 → | Mechanical / machine design Mechanical engineer | Shaft first critical speed (uniform, simply supported span) — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.3, S5-CALC-01 | 3 | |
| S5-CALC-10 Parked extreme wind on rotor and towerhigh agent runs CALC-10 → | Structural Structural engineer | Rotor and tower wind thrust, base reactions — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.8, S5-CALC-01 | 3 | |
| S5-CALC-11 Top bearing life (weight + operating radial load) and static safety at extreme wind agent runs CALC-11 → | Mechanical / machine design Mechanical engineer | Rolling bearing rating life (ISO 281 basic) and static safety — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.2, S5-CALC-01, S5-CALC-10 | 3 | |
| S5-CALC-12 Speed-up stage pinion bending (screening) agent runs CALC-12 → | Mechanical / machine design Mechanical engineer | Spur gear tooth bending (Lewis screening) — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.4, S5-CALC-01 | 3 | |
| S5-CALC-13 Clutch engagement onto a stationary generatorhigh agent runs CALC-13 → | Mechanical / machine design Mechanical engineer | Clutch engagement: torque, slip energy and temperature rise — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.5, S5-CALC-01 | 3 | |
| S5-CALC-14 Tower base flange bolts under parked extreme windhigh agent runs CALC-14 → | Mechanical / machine design Mechanical engineer | Bolted joint: preload, tightening torque, separation and slip — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.8, S5-CALC-10 | 3 | |
| S5-CALC-15 Spread footing: overturning, sliding, soil bearinghigh agent runs CALC-15 → | Civil and geotechnical Civil / geotechnical engineer | Square spread footing: overturning, sliding and soil bearing — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.9, S5-CALC-10 | 3 | |
| S5-CALC-16 Anchor rods: steel strength under factored extreme windhigh agent runs CALC-16 → | Structural Structural engineer | Anchor bolts on a bolt circle: tension and shear (steel strength) — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.9, S5-CALC-10 | 3 | |
| S5-LC-04 Simulate Emergency stop from overspeedmedium | Controls and software Controls engineer | Time-domain or spectrum result with assumptions ✓ Brake applied at 1.3 × rated speed, generators disengaged | S3-PLAN | 16 | |
| S5-LC-06 Simulate Fatigue spectrummedium | Mechanical / machine design Mechanical engineer | Time-domain or spectrum result with assumptions ✓ 20 years at the site distribution; 2P torque ripple on the shaft | S3-PLAN | 16 | |
| S5-LC-07 Simulate Loss of grid / load rejectionmedium | Controls and software Controls engineer | Time-domain or spectrum result with assumptions ✓ Electrical load drops to zero at rated; dump load and brake respond | S3-PLAN | 16 | |
| S5-FEAS Feasibility reportapprovalhigh | Systems engineering Systems engineer | Feasibility verdict with best/base/worst cases, unknowns, validation plan and cost to resolve uncertainty ✓ Verdict traceable to results; independent review requested for safety-critical items | S5-CALC-01, S5-CALC-02, S5-CALC-03, S5-CALC-04 +15 | 10 |
S6 Optimization and integration → Recommended configuration and trade study12 tasks · 53 hgate
Exit criteria: Interfaces compatible · Impacted calculations re-run
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S6-I-01 Define interface I-01: Rotor hub to top shaft segment: torque, weight and rotor bending moment | Mechanical / machine design Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-I-02 Define interface I-02: Top bearing housing to tower top: radial rotor loads and weight into the tower | Mechanical / machine design Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-I-04 Define interface I-04: Steady bearings to tower brackets: radial support only | Mechanical / machine design Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-I-05 Define interface I-05: Shaft bottom to gearbox input (coupling, axial float allowance for thermal growth of the long shaft) | Mechanical / machine design Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-I-06 Define interface I-06: Power take-off to each clutch | Mechanical / machine design Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-I-08 Define interface I-08: Magnet driver command to each clutch; engagement state feedback | Controls and software Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-I-09 Define interface I-09: Generator AC to rectifiers / DC bus | Controls and software Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-I-10 Define interface I-10: Brake release / apply and overspeed trip | Controls and software Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-I-11 Define interface I-11: Base plate to anchor rods: tension, compression and shear | Mechanical / machine design Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-I-12 Define interface I-12: Footing to soil: bearing pressure, sliding resistance | Mechanical / machine design Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-I-13 Define interface I-13: Generator and gearbox heat rejected from the house | Mechanical / machine design Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-TRADE Optimization trade studyapproval | Systems engineering Systems engineer | Recommended configuration (mass, cost, energy, reliability) with Pareto comparison ✓ Mandatory constraints hold in the recommended configuration | S5-FEAS, S6-I-01, S6-I-02, S6-I-04 +8 | 20 |
S7 Costing and roadmap → Costed development plan3 tasks · 20 hgate
Exit criteria: NRE separated from unit cost · Partner scopes, schedule and funding milestones
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S7-COST Cost model | Cost and funding Project controls | NRE vs recurring cost; prototype, pilot and production scenarios; contingency ✓ Quotes vs estimates labelled; currency, date, exclusions stated | S4-BOM, S6-TRADE | 8 | |
| S7-SCOPES Partner scopes | Systems engineering Project lead | Scopes of work for: Aerodynamics and fluids, Structural, Electrical power, Electronics / PCB (VX Design), Controls and software, Civil and geotechnical, Manufacturing ✓ Each scope lists inputs, deliverables, standards and sign-off | S6-TRADE | 6 | |
| S7-ROADMAP Development roadmap and funding milestonesapproval | Cost and funding Project lead | Schedule, budget per milestone, funding asks, contingencies ✓ Owner approves | S7-COST, S7-SCOPES | 6 |
S8 Handoff and later validation → Preliminary package, RFQs and test plan4 tasks · 34 hgate
Exit criteria: Drawings, models, calcs, BOM packaged · Specialist sign-offs listed · Not marked certified or construction-ready
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S8-VXD VX Design electronics handoff | Electronics / PCB (VX Design) Systems engineer | Structured VX Design intake package ✓ VX Design accepts the intake without open questions | S6-TRADE | 4 | |
| S8-RFQ RFQ packagesapproval | Sourcing and suppliers Buyer | Drawings, specs, quantities, tolerances, inspection and delivery requirements per supplier ✓ Owner approves before any external disclosure | S7-COST | 8 | |
| S8-TESTPLAN Prototype instrumentation and test plan | Test and validation Test engineer | Test procedures for 8 requirements verified by test/inspection/demonstration ✓ Every test-verified requirement has a procedure and pass criterion | S6-TRADE | 16 | |
| S8-PACKAGE Funding-ready preliminary packageapproval | Systems engineering Project lead | Brief, requirements, structure, BOM, calcs, feasibility, risks, costs, roadmap — marked preliminary ✓ Reviewer approval status shown on every document | S7-ROADMAP, S8-RFQ, S8-TESTPLAN, S8-VXD | 6 |