Risk register

Likelihood × severity (1–5 each). Mitigations become plan tasks or tests.

CodeRiskCause → effectL×SMitigationOwner
R-04Blade–strut joint fatigueVAWT cyclic aerodynamic loads at 2P → Blade loss4×5 = 20Joint fatigue test; conservative detail; inspection intervalStructural
R-01Staging gains less than claimedA single variable-speed generator with good MPPT is already efficient at part load → Weak value case for funders3×4 = 12Annual-energy comparison on measured generator maps; test both modes on one rigSystems engineering
R-02Long-shaft whirl and torsional resonanceSlender vertical shaft, couplings and tower flexibility → Vibration, bearing and coupling failure3×4 = 12Critical-speed and torsional analyses; steady bearings; rotordynamic reviewMechanical / machine design
R-03Clutch wear and heat under gusty cyclingFrequent engagements near threshold → Short clutch life, fade4×3 = 12Hysteresis and minimum-on timers; slip-energy budget; testMechanical / machine design
R-08Cost per kWh above conventional small windMore generators, clutches and a long shaft → No market3×4 = 12Cost model vs baselines; design to costCost and funding
R-06Overspeed on loss of loadGrid loss with all clutches released → Runaway rotor2×5 = 10Fail-safe spring brake, redundant speed sensing, dump loadControls and software
R-07Foundation under-designNo soil data → Tilt or overturning2×5 = 10Geotechnical report before construction; conservative preliminary sizeCivil and geotechnical
R-05Gearbox bearing failuresSmall-wind gearboxes historically fail at bearings → Downtime (mitigated by ground-level access)3×3 = 9Service factor ≥ 1.5; condition monitoring; ground-level swapMechanical / machine design
R-09Certification time and costIEC 61400-2 / ACP 101-1 testing → Delay before sales3×3 = 9Plan the test campaign early; pre-certification reviewStandards and compliance
R-10Freedom to operatePrior art in staged generators and VAWT drivetrains → IP dispute2×4 = 8Patent search by counsel (patents are concept references, not proof)Systems engineering