Risk register
Likelihood × severity (1–5 each). Mitigations become plan tasks or tests.
| Code | Risk | Cause → effect | L×S | Mitigation | Owner |
|---|---|---|---|---|---|
| R-04 | Blade–strut joint fatigue | VAWT cyclic aerodynamic loads at 2P → Blade loss | 4×5 = 20 | Joint fatigue test; conservative detail; inspection interval | Structural |
| R-01 | Staging gains less than claimed | A single variable-speed generator with good MPPT is already efficient at part load → Weak value case for funders | 3×4 = 12 | Annual-energy comparison on measured generator maps; test both modes on one rig | Systems engineering |
| R-02 | Long-shaft whirl and torsional resonance | Slender vertical shaft, couplings and tower flexibility → Vibration, bearing and coupling failure | 3×4 = 12 | Critical-speed and torsional analyses; steady bearings; rotordynamic review | Mechanical / machine design |
| R-03 | Clutch wear and heat under gusty cycling | Frequent engagements near threshold → Short clutch life, fade | 4×3 = 12 | Hysteresis and minimum-on timers; slip-energy budget; test | Mechanical / machine design |
| R-08 | Cost per kWh above conventional small wind | More generators, clutches and a long shaft → No market | 3×4 = 12 | Cost model vs baselines; design to cost | Cost and funding |
| R-06 | Overspeed on loss of load | Grid loss with all clutches released → Runaway rotor | 2×5 = 10 | Fail-safe spring brake, redundant speed sensing, dump load | Controls and software |
| R-07 | Foundation under-design | No soil data → Tilt or overturning | 2×5 = 10 | Geotechnical report before construction; conservative preliminary size | Civil and geotechnical |
| R-05 | Gearbox bearing failures | Small-wind gearboxes historically fail at bearings → Downtime (mitigated by ground-level access) | 3×3 = 9 | Service factor ≥ 1.5; condition monitoring; ground-level swap | Mechanical / machine design |
| R-09 | Certification time and cost | IEC 61400-2 / ACP 101-1 testing → Delay before sales | 3×3 = 9 | Plan the test campaign early; pre-certification review | Standards and compliance |
| R-10 | Freedom to operate | Prior art in staged generators and VAWT drivetrains → IP dispute | 2×4 = 8 | Patent search by counsel (patents are concept references, not proof) | Systems engineering |