VX Inventor · preliminary feasibility package · 2026-11-25
Vertical-transmission wind turbine
A wind rotor drives a vertical shaft down the tower to staged, clutch-engaged generators at ground level.
1. Executive concept brief
The rotor's torque travels down a vertical transmission shaft inside the tower to a ground-level generator house. There, a speed-up gear stage feeds a bank of generators that are engaged one at a time by magnetically controlled centrifugal clutches as the available power rises, so each engaged generator runs near its efficient load point, and every heavy, serviceable part sits at ground level instead of at the top of the tower.
- Function
- Generate electricity from wind with high part-load efficiency and ground-level maintenance of the drivetrain.
- Environment
- Outdoor, rural/suburban site, −20 to +45 °C, corrosivity C3, IEC small-wind class III (assumed).
- Scale
- Small wind: ≈ 12 m² swept area, ≈ 3–4 kW rated (prototype scale); architecture intended to scale.
- Budget
- Not yet stated (gap G-10).
2. Feasibility
Conditional feasibility. All 15 mandatory calculations pass on the stated assumptions.
- G-01: Import the patent / design documents for the vertical transmission and the staged clutch arrangement.
- G-02: Is the rotor a vertical-axis rotor on top of the tower, or a horizontal-axis rotor with a right-angle gear into the vertical shaft?
- G-05: How does the magnet control the centrifugal clutch (hold shoes retracted, add engagement force, or release a latch)? Are thresholds set by speed or by power?
- G-08: Prototype budget and the funding target.
- A-01 must be confirmed: Rotor is a 3-blade H-type vertical-axis rotor, 3 m diameter × 4 m high, on top of the tower.
- A-02 must be confirmed: Rotor power coefficient Cp = 0.30 at tip-speed ratio 3 (mid-range of published H-rotor tests).
- A-03 must be confirmed: Site wind: annual mean 6 m/s at rotor height, Rayleigh distribution (no site data yet).
- A-05 must be confirmed: Three 1.5 kW permanent-magnet generators behind a 6.5:1 speed-up stage.
- A-07 must be confirmed: Allowable soil bearing 150 kPa, friction 0.45 (no geotechnical report).
- A-11 must be confirmed: Clutch: a centrifugal shoe clutch whose engagement is held off or released by an electromagnet, so a controller can set the engagement threshold by power.
- CALC-10: Static preliminary load: gust, dynamic and code load factors must be applied by the structural engineer
- CALC-11: Basic life only: run the maker's calculator (a_ISO, lubrication, contamination) before selection
- CALC-12: Lewis screening only: rate to AGMA 2001 / ISO 6336 (bending and contact) before selection
- CALC-15: eccentricity 0.87 m exceeds B/6 = 0.58 m: part of the base lifts off the soil (allowed by some codes for wind, not for sustained loads)
- CALC-16: Steel strength only: concrete breakout, pull-out and side-face blowout govern many tower anchorages (ACI 318 ch. 17)
3. Requirements
| REQ-PERF-001 | Rated electrical output at 12 m/s hub wind speed. | ≥ 3.0 kW electrical at 12 m/s | assumed |
| REQ-PERF-002 | Begin producing power at low wind speed. | cut-in ≤ 3.5 m/s | test planned |
| REQ-PERF-003 | Staged generator engagement shall raise part-load conversion efficiency compared with one generator of the same total rating. | ≥ +5 % electrical output at 6 m/s | assumed |
| REQ-PERF-004 | Annual energy production shall be reported against conventional geared and direct-drive baselines with the same rotor. | AEP at 6 m/s Rayleigh, with uncertainty | assumed |
| REQ-SAFE-001 | Survive the 50-year extreme wind parked without structural failure. | Ve50 = 52.5 m/s (IEC 61400-2 class III) | assumed |
| REQ-SAFE-002 | A fail-safe brake shall stop and hold the rotor on overspeed or loss of load/grid. | stop from 1.3× rated speed; PL c or better (ISO 13849) | test planned |
| REQ-SAFE-003 | All rotating parts accessible at ground level shall be guarded. | ISO 12100 / ISO 13857 distances | test planned |
| REQ-INT-001 | The vertical shaft shall run clear of its bending critical speeds. | critical / max running speed ≥ 1.25 | assumed |
| REQ-STR-001 | The foundation shall resist overturning and sliding and stay within allowable soil bearing. | FS ≥ 1.5 overturning and sliding; q ≤ q_allow | assumed |
| REQ-LIFE-001 | Design life. | 20 years | assumed |
| REQ-LIFE-002 | Rolling bearings shall reach their rating life without replacement. | L10 ≥ 100 000 h | assumed |
| REQ-MAINT-001 | Generators, clutches, brake and gearbox shall be replaceable from ground level without climbing or a crane. | ≤ 4 h per generator swap, 2 people | test planned |
| REQ-ENV-001 | Operating environment. | −20 to +45 °C; ISO 12944 C3; enclosures IP54 min | none |
| REQ-ENV-002 | Noise at the nearest dwelling. | ≤ local limit (typ. 45 dB(A) at night) | test planned |
| REQ-REG-001 | Follow a recognised small-wind certification path. | IEC 61400-2 or ANSI/ACP 101-1 | test planned |
| REQ-REG-002 | Grid-connected operation shall use listed interconnection equipment. | UL 1741 / IEEE 1547 | test planned |
| REQ-COST-001 | Prototype build cost and levelised cost of energy shall be estimated against the baselines. | costed range with exclusions | none |
4. Product structure
| 1 | Vertical-transmission wind turbine | Systems engineering | tbd |
| 1.1 | Rotor | Aerodynamics and fluids | tbd |
| 1.1.1 | Blades (H-rotor, pultruded aerofoil) ×3 | Aerodynamics and fluids | make |
| 1.1.2 | Blade struts / arms ×6 | Structural | make |
| 1.1.3 | Rotor hub | Mechanical / machine design | make |
| 1.1.4 | Blade and strut fasteners ×36 | Mechanical / machine design | buy |
| 1.2 | Top bearing and rotor support | Mechanical / machine design | tbd |
| 1.2.1 | Top radial bearing (spherical roller) | Mechanical / machine design | buy |
| 1.2.2 | Thrust bearing carrying rotor and shaft weight | Mechanical / machine design | buy |
| 1.2.3 | Bearing housing, seals and lubrication | Mechanical / machine design | make |
| 1.3 | Vertical transmission shaft | Mechanical / machine design | tbd |
| 1.3.1 | Shaft segments ×3 | Mechanical / machine design | make |
| 1.3.2 | Segment couplings (disc type) ×2 | Mechanical / machine design | buy |
| 1.3.3 | Intermediate steady bearings ×2 | Mechanical / machine design | buy |
| 1.3.4 | Steady-bearing brackets in tower ×2 | Structural | make |
| 1.4 | Ground-level gear stage | Mechanical / machine design | tbd |
| 1.4.1 | Speed-up gearbox (planetary or helical) | Mechanical / machine design | buy |
| 1.4.2 | Power take-off to generator branches | Mechanical / machine design | make |
| 1.4.3 | Gearbox lubricant | Mechanical / machine design | buy |
| 1.5 | Staged generator bank | Electrical power | tbd |
| 1.5.1 | Magnetically controlled centrifugal clutches ×3 | Mechanical / machine design | make |
| 1.5.2 | Permanent-magnet generators 1.5 kW ×3 | Electrical power | buy |
| 1.5.3 | Generator couplings (jaw) ×3 | Mechanical / machine design | buy |
| 1.5.4 | Clutch magnet drivers and engagement controller | Electronics / PCB (VX Design) | make |
| 1.6 | Braking and overspeed protection | Controls and software | tbd |
| 1.6.1 | Spring-applied fail-safe brake | Mechanical / machine design | buy |
| 1.6.2 | Redundant overspeed sensing ×2 | Controls and software | buy |
| 1.7 | Power electronics, controls and electrical | Electrical power | tbd |
| 1.7.1 | Supervisory controller | Electronics / PCB (VX Design) | make |
| 1.7.2 | Rectifiers, DC bus and listed hybrid inverter | Electrical power | buy |
| 1.7.3 | Dump load / diversion resistor | Electrical power | buy |
| 1.7.4 | Sensors: anemometer, shaft speed/torque, vibration, temperatures | Controls and software | buy |
| 1.7.5 | Enclosures, disconnects, wiring and earthing | Electrical power | buy |
| 1.8 | Tower | Structural | tbd |
| 1.8.1 | Tubular steel tower, flanged sections | Structural | make |
| 1.8.2 | Tower base flange bolts (M24, class 10.9) ×16 | Structural | buy |
| 1.8.3 | Tower base plate | Structural | make |
| 1.8.4 | Service access: hatch, climbing / tower-lowering provision | Structural | make |
| 1.9 | Foundation | Civil and geotechnical | tbd |
| 1.9.1 | Reinforced-concrete spread footing | Civil and geotechnical | make |
| 1.9.2 | Reinforcement | Civil and geotechnical | buy |
| 1.9.3 | Anchor rods (M30, F1554 Gr 55) and setting template ×12 | Structural | buy |
| 1.9.4 | Base-plate grout | Civil and geotechnical | buy |
| 1.9.5 | Earthing electrode and lightning protection | Electrical power | buy |
| 1.10 | Generator house, guards and service provisions | Manufacturing | tbd |
| 1.10.1 | Weatherproof generator house | Manufacturing | make |
| 1.10.2 | Guards on rotating parts | Manufacturing | make |
| 1.10.3 | Lifting points and generator slide rails | Manufacturing | make |
5. Engineering calculations
| CALC-01 | Rotor power, speed and torque at rated wind | Swept area 12 m²; Power in the wind (Cp = 1) 12.7 kW; Rotor shaft power 3.81 kW | pass |
| CALC-02 | Rotor power at the site mean wind (part load) | Swept area 12 m²; Power in the wind (Cp = 1) 1.588 kW; Rotor shaft power 0.4763 kW | pass |
| CALC-03 | Annual energy production at the site | Weibull scale c 6.77 m/s; Rated rotor power 3.81 kW; Mean electrical power 0.6661 kW | pass |
| CALC-04 | Staged generator bank at rated power | Power at generator shaft 3.618 kW; Generators engaged 3 ; Load on each engaged generator 80.39 % | pass |
| CALC-05 | Staged generator bank at part load: staged vs one generator | Power at generator shaft 0.4172 kW; Generators engaged 1 ; Load on each engaged generator 27.82 % | pass |
| CALC-06 | Energy balance at rated: no output beyond input | Implied efficiency 85.85 %; Unaccounted losses 4.00e-5 kW | pass |
| CALC-07 | Vertical shaft fatigue at rated torque with 2P ripple | von Mises alternating stress σa' 6.84 MPa; von Mises mean stress σm' 9.725 MPa; Corrected endurance limit Se 227.6 MPa | pass |
| CALC-08 | Shaft critical speed with two steady bearings (3 spans) | First critical speed 663.4 rpm; Critical / running speed 2.227 ; Longest span keeping the margin 4.404 m | pass |
| CALC-09 | Rejected option: one 10 m span with no steady bearings (rejected alternative) | First critical speed 72.24 rpm; Critical / running speed 0.2425 ; Longest span keeping the margin 4.404 m | fail |
| CALC-10 | Parked extreme wind on rotor and tower | Velocity pressure 1,688 Pa; Rotor force 24.31 kN; Tower force 6.483 kN | warn |
| CALC-11 | Top bearing life (weight + operating radial load) and static safety at extreme wind | Equivalent dynamic load P 14.24 kN; Basic rating life L10 6,687 Mrev; Basic rating life L10h 486,300 h | warn |
| CALC-12 | Speed-up stage pinion bending (screening) | Pitch diameter 54 mm; Tangential load Wt 1,357 N; Pitch-line velocity 4.212 m/s | warn |
| CALC-13 | Clutch engagement onto a stationary generator | Torque needed 3.12 N·m; Slip heat per engagement 0.365 kJ; Plate temperature rise per engagement 0.7935 K | pass |
| CALC-14 | Tower base flange bolts under parked extreme wind | Tensile stress area As 352.5 mm²; Proof load per bolt 292.6 kN; Preload per bolt 204.8 kN | pass |
| CALC-15 | Spread footing: overturning, sliding, soil bearing | Footing weight 231.3 kN; Soil cover weight 110.3 kN; Total stabilising vertical load 356.5 kN | warn |
| CALC-16 | Anchor rods: steel strength under factored extreme wind | Peak anchor tension 111 kN; Shear per anchor 2.566 kN; Design tensile strength φNsa 217.4 kN | warn |
6. Assumptions and open questions
- A-01 (high): Rotor is a 3-blade H-type vertical-axis rotor, 3 m diameter × 4 m high, on top of the tower.
- A-02 (high): Rotor power coefficient Cp = 0.30 at tip-speed ratio 3 (mid-range of published H-rotor tests).
- A-03 (high): Site wind: annual mean 6 m/s at rotor height, Rayleigh distribution (no site data yet).
- A-04 (medium): IEC 61400-2 class III: Vref 37.5 m/s, 50-year extreme Ve50 = 52.5 m/s.
- A-05 (high): Three 1.5 kW permanent-magnet generators behind a 6.5:1 speed-up stage.
- A-06 (medium): Generator losses: 10 % at rated, 35 % of that fixed (core, friction, windage).
- A-07 (high): Allowable soil bearing 150 kPa, friction 0.45 (no geotechnical report).
- A-08 (medium): Rotor centre 10 m above grade; tower Ø 0.4 m × 8 m.
- A-09 (medium): Shaft: solid Ø 60 mm AISI 4140 Q&T in three segments; torque ripple ±50 % of mean (2-blade-pass excitation of a VAWT).
- A-10 (medium): Parked rotor drag coefficient 1.2 on projected area (conservative).
- A-11 (high): Clutch: a centrifugal shoe clutch whose engagement is held off or released by an electromagnet, so a controller can set the engagement threshold by power.
- G-01 [blocking] Import the patent / design documents for the vertical transmission and the staged clutch arrangement.
- G-02 [blocking] Is the rotor a vertical-axis rotor on top of the tower, or a horizontal-axis rotor with a right-angle gear into the vertical shaft?
- G-03 [assumable] Where will the prototype stand? Site wind data (or a nearby met station) and the permitting authority.
- G-04 [assumable] Geotechnical report: allowable bearing, friction, frost depth, water table.
- G-05 [blocking] How does the magnet control the centrifugal clutch (hold shoes retracted, add engagement force, or release a latch)? Are thresholds set by speed or by power?
- G-06 [assumable] Which generators: maker, rated speed, efficiency map, inertia?
- G-07 [deferred] Grid-tied, battery-based or both?
- G-08 [blocking] Prototype budget and the funding target.
- G-09 [deferred] Local noise and setback limits.
7. Risks
- R-01 Staging gains less than claimed (3×4) — Annual-energy comparison on measured generator maps; test both modes on one rig
- R-02 Long-shaft whirl and torsional resonance (3×4) — Critical-speed and torsional analyses; steady bearings; rotordynamic review
- R-03 Clutch wear and heat under gusty cycling (4×3) — Hysteresis and minimum-on timers; slip-energy budget; test
- R-04 Blade–strut joint fatigue (4×5) — Joint fatigue test; conservative detail; inspection interval
- R-05 Gearbox bearing failures (3×3) — Service factor ≥ 1.5; condition monitoring; ground-level swap
- R-06 Overspeed on loss of load (2×5) — Fail-safe spring brake, redundant speed sensing, dump load
- R-07 Foundation under-design (2×5) — Geotechnical report before construction; conservative preliminary size
- R-08 Cost per kWh above conventional small wind (3×4) — Cost model vs baselines; design to cost
- R-09 Certification time and cost (3×3) — Plan the test campaign early; pre-certification review
- R-10 Freedom to operate (2×4) — Patent search by counsel (patents are concept references, not proof)
8. Cost and roadmap
Unit cost $24,012–$70,323; NRE $90,225–$255,388 incl. contingency. Prototype: $114,237–$325,710; Pilot: $139,947–$409,854; Production: $815,639–$2,388,712. Estimates, not quotes (2026-11-25).
| S1 Concept intake | Concept brief and open-question register | 22 h |
| S2 Requirements and concept | Requirements baseline and selected concept | 20 h |
| S3 Decomposition and plan | Approved development plan | 41 h |
| S4 Preliminary engineering and sourcing | Traceable preliminary design and assumptions | 314 h |
| S5 Simulation and feasibility | Feasibility report and alternatives | 106 h |
| S6 Optimization and integration | Recommended configuration and trade study | 53 h |
| S7 Costing and roadmap | Costed development plan | 20 h |
| S8 Handoff and later validation | Preliminary package, RFQs and test plan | 34 h |
Exclusions: Full certification testing; Land, grid-connection fees; Taxes and duties; Patent prosecution; Operating and maintenance costs (reported separately once a duty cycle is agreed).