Reference projects / Solar HiveConditional feasibility
Reference project — read-only and public. Every number on these pages is computed live by the calculation engine from the stated design basis. Copy it into a project to change assumptions, resolve gaps and work with the agent.
Cost model and BOM
Estimates in USD, dated 2026-11-25. Quotes and estimates are labelled; nonrecurring engineering (NRE) is separated from recurring unit cost (spec §07).
Unit cost (parts + assembly)$8,165 – $24,265
NRE incl. contingency$52,108 – $150,530
Prototype (1 unit)$60,273 – $174,795$8,165–$24,265 per unit
Pilot (10 units)$47,587 – $141,421$4,759–$14,142 per unit
Production (100 units)$277,348 – $824,233$2,773–$8,242 per unit
Cost lines
| Line | Kind | Low | High | Basis |
|---|---|---|---|---|
| Parts and materials (BOM roll-up) | recurring | $7,100 | $21,100 | estimates — not quotes |
| Assembly, inspection and freight (15 % of parts) | recurring | $1,065 | $3,165 | rule of thumb |
| Engineering (329 h from the plan at $120/h, ±30 %) | nre | $27,636 | $51,324 | plan estimate |
| Prototype testing and instrumentation | nre | $3,550 | $21,100 | allowance: 50–100 % of one unit's parts |
| Independent specialist review (structural, geotechnical, mechanical) | nre | $4,000 | $15,000 | allowance |
| Permits and site work | nre | $1,500 | $8,000 | allowance; jurisdiction-dependent |
| Certification path (pre-assessment; full certification excluded) | nre | $5,000 | $25,000 | allowance |
Assumptions
- Engineering rate $120/h
- Contingency 25 % on NRE
- Learning curve 85 % per doubling (applied to unit cost)
- Part costs are estimates unless marked supplier_data
Exclusions
- Full certification testing
- Land, grid-connection fees
- Taxes and duties
- Patent prosecution
- Operating and maintenance costs (reported separately once a duty cycle is agreed)
Preliminary BOM
| Item | Name | Qty | Make/buy | Low | High | Basis |
|---|---|---|---|---|---|---|
| 1.1.1 | PV laminates cut / built to hexagonal format | 7 | tbd | $1,400 | $4,200 | assumed |
| 1.1.2 | Hexagonal cell frames | 7 | make | $700 | $2,100 | assumed |
| 1.1.3 | Cell-to-hub quick connectors | 7 | make | $200 | $600 | assumed |
| 1.1.4 | DC wiring, connectors and bonding | 1 | buy | $150 | $500 | assumed |
| 1.2.1 | Azimuth slew drive | 1 | buy | $500 | $1,500 | assumed |
| 1.2.2 | Elevation actuator | 1 | buy | $250 | $800 | assumed |
| 1.2.3 | Hub slewing bearing | 1 | buy | $400 | $1,200 | assumed |
| 1.2.4 | Tracker controller with wind-stow | 1 | make | $300 | $1,200 | assumed |
| 1.3.1 | Steel mast tube | 1 | make | $600 | $1,800 | assumed |
| 1.3.2 | Mast base plate and flange bolts | 1 | make | $250 | $700 | assumed |
| 1.4.1 | Reinforced-concrete pad | 1 | make | $1,500 | $4,000 | assumed |
| 1.4.2 | Anchor rods | 8 | buy | $250 | $700 | assumed |
| 1.5.1 | Microinverters or string inverter with MLPE | 1 | buy | $600 | $1,800 | assumed |