Reference projects / Solar HiveConditional feasibility
Reference project — read-only and public. Every number on these pages is computed live by the calculation engine from the stated design basis. Copy it into a project to change assumptions, resolve gaps and work with the agent.
Development plan
45 tasks, 329 engineering hours, 8 approval gates. Every task has a deliverable, inputs, method, dependencies, role, estimate and acceptance criterion; work stops at testable packages (spec §03). Critical path ≈ 17 working days if each task has one person.
S1 Concept intake → Concept brief and open-question register3 tasks · 14 h
Exit criteria: Function, environment, budget, scale and constraints captured · Source documents imported or listed as missing
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S1-BRIEF Concept brief and open-question register | Systems engineering Systems engineer | Concept brief v1 with open-question register ✓ Brief states function, environment, scale, budget and constraints; every unknown is in the register | 6 | ||
| S1-G-01 Resolve G-01: Import the Solar Hive description, sketches or patent: what does it do differently from a conventional array?high | Systems engineering Systems engineer | Answer recorded with its source, or an approved assumption ✓ Gap closed or reclassified with reason | S1-BRIEF | 4 | |
| S1-G-02 Resolve G-02: Custom hexagonal laminates, or standard certified modules in hexagonal frames?high | Electrical power Electrical engineer | Answer recorded with its source, or an approved assumption ✓ Gap closed or reclassified with reason | S1-BRIEF | 4 |
S2 Requirements and concept → Requirements baseline and selected concept2 tasks · 20 hgate
Exit criteria: Measurable performance targets · Jurisdiction, design life and safety requirements set · Alternative concepts compared
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S2-REQ Requirements baselineapprovalmedium | Systems engineering Systems engineer | Requirements baseline (8 requirements) with measurable targets ✓ Every requirement measurable and verifiable; inventor approves | S1-BRIEF, S1-G-01, S1-G-02 | 8 | |
| S2-CONCEPTS Alternative concepts and baselinesapprovalmedium | Systems engineering Systems engineer | Concept comparison incl. conventional baselines; schematic diagrams ✓ Selected concept recorded with reasons | S2-REQ | 12 |
S3 Decomposition and plan → Approved development plan3 tasks · 27 hgate
Exit criteria: Every function mapped to a subsystem · Every part has discipline, analyses, standards and acceptance test · Dependency-ordered task graph approved
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S3-DECOMP System decomposition review | Systems engineering Systems engineer | Product structure (19 items) with functions and interfaces ✓ No orphan function or requirement; every part has discipline, analyses, standards and acceptance test | S2-CONCEPTS | 8 | |
| S3-STANDARDS Standards applicability matrix | Standards and compliance Compliance engineer | Applicability matrix for 16 standards; acquisition tasks for missing documents ✓ Each standard: edition identified, acquired or purchase task raised, clauses mapped | S3-DECOMP | 16 | |
| S3-PLAN Approve the development planapproval | Systems engineering Project lead | Approved development plan and staffing ✓ Inventor / owner approves | S3-DECOMP, S3-STANDARDS | 3 |
S4 Preliminary engineering and sourcing → Traceable preliminary design and assumptions18 tasks · 162 h
Exit criteria: Load paths established · Candidate materials and commercial parts selected · Preliminary BOM
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S4-DES-1.1 Preliminary design: Hexagonal PV cellsmedium | Electrical power Electrical engineer | Layout, load path, parametric CAD and assumptions list ✓ Load path closed; every part sized or sourced | S3-PLAN | 16 | |
| S4-DES-1.2 Preliminary design: Tracking headmedium | Mechanical / machine design Mechanical engineer | Layout, load path, parametric CAD and assumptions list ✓ Load path closed; every part sized or sourced | S3-PLAN | 16 | |
| S4-DES-1.3 Preliminary design: Mastmedium | Structural Structural engineer | Layout, load path, parametric CAD and assumptions list ✓ Load path closed; every part sized or sourced | S3-PLAN | 16 | |
| S4-DES-1.4 Preliminary design: Foundationmedium | Civil and geotechnical Civil / geotechnical engineer | Layout, load path, parametric CAD and assumptions list ✓ Load path closed; every part sized or sourced | S3-PLAN | 16 | |
| S4-DES-1.5 Preliminary design: Power conversion and interconnection | Electrical power Electrical engineer | Layout, load path, parametric CAD and assumptions list ✓ Load path closed; every part sized or sourced | S3-PLAN | 16 | |
| S4-PART-1.1.1 Detail: PV laminates cut / built to hexagonal format | Electrical power Electrical engineer | Part record: geometry envelope, material grade and condition, tolerances, process ✓ Custom-format laminates need their own IEC 61215 qualification — or use standard rectangular modules in hex frames | S4-DES-1.1 | 10 | |
| S4-PART-1.1.2 Detail: Hexagonal cell frames | Structural Structural engineer | Part record: geometry envelope, material grade and condition, tolerances, process ✓ Frame carries 2400 Pa wind / 5400 Pa snow test loads | S4-DES-1.1 | 10 | |
| S4-PART-1.1.3 Detail: Cell-to-hub quick connectors | Mechanical / machine design Mechanical engineer | Part record: geometry envelope, material grade and condition, tolerances, process ✓ Cell swap without tools in ≤ 30 min; bonding path maintained | S4-DES-1.1 | 10 | |
| S4-SRC-1.1.4 Source: DC wiring, connectors and bonding | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.1 | 3 | |
| S4-SRC-1.2.1 Source: Azimuth slew drive | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.2 | 3 | |
| S4-SRC-1.2.2 Source: Elevation actuator | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.2 | 3 | |
| S4-SRC-1.2.3 Source: Hub slewing bearing | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.2 | 3 | |
| S4-PART-1.3.1 Detail: Steel mast tube | Structural Structural engineer | Part record: geometry envelope, material grade and condition, tolerances, process ✓ Member checks by structural engineer | S4-DES-1.3 | 10 | |
| S4-PART-1.3.2 Detail: Mast base plate and flange bolts | Structural Structural engineer | Part record: geometry envelope, material grade and condition, tolerances, process ✓ Plate and bolt checks | S4-DES-1.3 | 10 | |
| S4-PART-1.4.1 Detail: Reinforced-concrete pad | Civil and geotechnical Civil / geotechnical engineer | Part record: geometry envelope, material grade and condition, tolerances, process ✓ FS ≥ 1.5; bearing within allowable | S4-DES-1.4 | 10 | |
| S4-SRC-1.4.2 Source: Anchor rods | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.4 | 3 | |
| S4-SRC-1.5.1 Source: Microinverters or string inverter with MLPE | Sourcing and suppliers Buyer | Candidate part numbers (≥ 2 makers), datasheets, price and lead time ✓ Ratings meet the sizing result with reserve; quote dated | S4-DES-1.5 | 3 | |
| S4-BOM Preliminary BOM | Sourcing and suppliers Buyer | Part-level BOM with make/buy, quantities, cost ranges and lead times ✓ Every part has quantity, make/buy and a cost range with its basis | S4-PART-1.1.1, S4-PART-1.1.2, S4-PART-1.1.3, S4-SRC-1.1.4 +8 | 4 |
S5 Simulation and feasibility → Feasibility report and alternatives6 tasks · 25 hgate
Exit criteria: Energy balance closes · Mandatory criteria checked · Uncertainty quantified
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S5-CALC-01 Cluster output at peak sun, tracked annual energyhigh agent runs CALC-01 → | Electrical power Electrical engineer | Photovoltaic array output and annual yield — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.1 | 3 | |
| S5-CALC-02 Same modules on a fixed-tilt baselinehigh agent runs CALC-02 → | Electrical power Electrical engineer | Photovoltaic array output and annual yield — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.1 | 3 | |
| S5-CALC-03 Design wind on the stowed cluster and masthigh agent runs CALC-03 → | Structural Structural engineer | Rotor and tower wind thrust, base reactions — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.3 | 3 | |
| S5-CALC-04 Mast pad: overturning, sliding, bearinghigh agent runs CALC-04 → | Civil and geotechnical Civil / geotechnical engineer | Square spread footing: overturning, sliding and soil bearing — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.4, S5-CALC-03 | 3 | |
| S5-CALC-05 Mast anchor rods (steel strength)high agent runs CALC-05 → | Structural Structural engineer | Anchor bolts on a bolt circle: tension and shear (steel strength) — result with checks and validity ✓ Result recorded with inputs, version and fingerprint; mandatory checks pass or are escalated | S4-DES-1.4, S5-CALC-03 | 3 | |
| S5-FEAS Feasibility reportapprovalhigh | Systems engineering Systems engineer | Feasibility verdict with best/base/worst cases, unknowns, validation plan and cost to resolve uncertainty ✓ Verdict traceable to results; independent review requested for safety-critical items | S5-CALC-01, S5-CALC-02, S5-CALC-03, S5-CALC-04 +1 | 10 |
S6 Optimization and integration → Recommended configuration and trade study6 tasks · 35 hgate
Exit criteria: Interfaces compatible · Impacted calculations re-run
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S6-I-01 Define interface I-01: Cell frame to hub connector: wind and snow load path, bonding | Mechanical / machine design Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-I-02 Define interface I-02: Cluster hub to tracking head bearing | Mechanical / machine design Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-I-03 Define interface I-03: Controller to slew drive and actuator | Controls and software Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-I-04 Define interface I-04: Mast base plate to anchor rods | Mechanical / machine design Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-I-05 Define interface I-05: Cell DC outputs to inverters | Controls and software Systems engineer | Interface control sheet: geometry, loads, fits, signals, ownership ✓ Both owners sign; dependent calculations re-run | S5-FEAS | 3 | |
| S6-TRADE Optimization trade studyapproval | Systems engineering Systems engineer | Recommended configuration (mass, cost, energy, reliability) with Pareto comparison ✓ Mandatory constraints hold in the recommended configuration | S5-FEAS, S6-I-01, S6-I-02, S6-I-03 +2 | 20 |
S7 Costing and roadmap → Costed development plan3 tasks · 20 hgate
Exit criteria: NRE separated from unit cost · Partner scopes, schedule and funding milestones
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S7-COST Cost model | Cost and funding Project controls | NRE vs recurring cost; prototype, pilot and production scenarios; contingency ✓ Quotes vs estimates labelled; currency, date, exclusions stated | S4-BOM, S6-TRADE | 8 | |
| S7-SCOPES Partner scopes | Systems engineering Project lead | Scopes of work for: Electrical power, Structural, Electronics / PCB (VX Design), Civil and geotechnical ✓ Each scope lists inputs, deliverables, standards and sign-off | S6-TRADE | 6 | |
| S7-ROADMAP Development roadmap and funding milestonesapproval | Cost and funding Project lead | Schedule, budget per milestone, funding asks, contingencies ✓ Owner approves | S7-COST, S7-SCOPES | 6 |
S8 Handoff and later validation → Preliminary package, RFQs and test plan4 tasks · 26 hgate
Exit criteria: Drawings, models, calcs, BOM packaged · Specialist sign-offs listed · Not marked certified or construction-ready
| Task | Discipline / role | Deliverable and acceptance | Depends on | h | Schedule |
|---|---|---|---|---|---|
| S8-VXD VX Design electronics handoff | Electronics / PCB (VX Design) Systems engineer | Structured VX Design intake package ✓ VX Design accepts the intake without open questions | S6-TRADE | 4 | |
| S8-RFQ RFQ packagesapproval | Sourcing and suppliers Buyer | Drawings, specs, quantities, tolerances, inspection and delivery requirements per supplier ✓ Owner approves before any external disclosure | S7-COST | 8 | |
| S8-TESTPLAN Prototype instrumentation and test plan | Test and validation Test engineer | Test procedures for 4 requirements verified by test/inspection/demonstration ✓ Every test-verified requirement has a procedure and pass criterion | S6-TRADE | 8 | |
| S8-PACKAGE Funding-ready preliminary packageapproval | Systems engineering Project lead | Brief, requirements, structure, BOM, calcs, feasibility, risks, costs, roadmap — marked preliminary ✓ Reviewer approval status shown on every document | S7-ROADMAP, S8-RFQ, S8-TESTPLAN, S8-VXD | 6 |