Reference projects / Solar HiveConditional feasibility
Reference project — read-only and public. Every number on these pages is computed live by the calculation engine from the stated design basis. Copy it into a project to change assumptions, resolve gaps and work with the agent.
Risk register
Likelihood × severity (1–5 each). Mitigations become plan tasks or tests.
| Code | Risk | Cause → effect | L×S | Mitigation | Owner |
|---|---|---|---|---|---|
| R-02 | Custom laminate certification | Hexagonal format is not a stock module → Cost and 6–12 month delay | 4×4 = 16 | Prefer certified modules in hex frames | Standards and compliance |
| R-01 | Tracking gain does not pay for the tracker | Module prices are low; trackers add cost and maintenance → Worse cost per kWh than fixed tilt | 3×4 = 12 | Cost-per-kWh comparison with fixed tilt and single-axis | Cost and funding |
| R-04 | Wind overturning on a single mast | Large sail area on one support → Mast or foundation failure | 2×5 = 10 | Stow logic with redundancy; structural review | Structural |
| R-03 | Self-shading inside the cluster | Cells around a hub shade each other at low sun → Lower yield, hot spots | 3×3 = 9 | Shading model; MLPE per cell | Electrical power |