Reference projects / Solar HiveConditional feasibility
Reference project — read-only and public. Every number on these pages is computed live by the calculation engine from the stated design basis. Copy it into a project to change assumptions, resolve gaps and work with the agent.
Gaps, assumptions and findings
The agent never silently invents dimensions, loads, allowables or supplier data: what is missing is a gap (blocking, assumable with bounded sensitivity, or deferred), and what is assumed says so.
Open questions
| Code | Question | Class | Discipline | Why it matters |
|---|---|---|---|---|
| G-01 | Import the Solar Hive description, sketches or patent: what does it do differently from a conventional array? | blocking | Systems engineering | The current architecture is a placeholder; nothing can be approved until the invention is described. |
| G-02 | Custom hexagonal laminates, or standard certified modules in hexagonal frames? | blocking | Electrical power | Custom laminates need their own IEC 61215/61730 qualification — a major cost and schedule item. |
| G-03 | Site, permitting authority and grid connection. Proposed: A-03, A-04 | assumable | Standards and compliance | Sets wind/snow loads and electrical code. |
| G-04 | Geotechnical data. Proposed: A-05 | assumable | Civil and geotechnical | Foundation size. |
Assumptions
| Code | Assumption | Value | Sensitivity | Affects | Status |
|---|---|---|---|---|---|
| A-01 | PLACEHOLDER: 'hive' = 7 hexagonal PV cells around a central hub on a dual-axis tracking mast. | — | high | 1 | unapproved |
| A-02 | Active cell area 10 m² at 21.5 % module efficiency. | 10 m², 21.5 % | high | 1.1 | unapproved |
| A-03 | Site: 4.5 peak sun hours fixed tilt; dual-axis tracking raises this to ≈ 6.0. | PSH 6.0 (tracked) | high | 1.1 | unapproved |
| A-04 | Design wind 50 m/s, cluster stowed flat (drag coefficient 1.3 on 30 % projected area). | 50 m/s | medium | 1.3, 1.4 | unapproved |
| A-05 | Allowable soil bearing 150 kPa, friction 0.45. | 150 kPa | high | 1.4 | unapproved |
Design review findings
Blocking 2
- blocking G-01: Import the Solar Hive description, sketches or patent: what does it do differently from a conventional array?
- blocking G-02: Custom hexagonal laminates, or standard certified modules in hexagonal frames?
Warnings 11
- assumable G-03: Site, permitting authority and grid connection.
- assumable G-04: Geotechnical data.
- completeness 1.2.4 Tracker controller with wind-stow has no parts yet: decompose it to a testable work package or mark it bought.
- completeness No seals in the product structure. Every machine needs them somewhere — add them or state why not.
- completeness No lubrication in the product structure. Every machine needs them somewhere — add them or state why not.
- completeness No sensors / instrumentation in the product structure. Every machine needs them somewhere — add them or state why not.
- completeness No service access in the product structure. Every machine needs them somewhere — add them or state why not.
- assumable High-sensitivity assumption A-01 not yet approved: PLACEHOLDER: 'hive' = 7 hexagonal PV cells around a central hub on a dual-axis tracking mast.
- assumable High-sensitivity assumption A-02 not yet approved: Active cell area 10 m² at 21.5 % module efficiency.
- assumable High-sensitivity assumption A-03 not yet approved: Site: 4.5 peak sun hours fixed tilt; dual-axis tracking raises this to ≈ 6.0.
- assumable High-sensitivity assumption A-05 not yet approved: Allowable soil bearing 150 kPa, friction 0.45.
Information 15
- completeness 1.1.1 PV laminates cut / built to hexagonal format: make, buy or reuse not decided.
- completeness Interface I-01 (structural) not yet defined: Cell frame to hub connector: wind and snow load path, bonding.
- completeness Interface I-02 (structural) not yet defined: Cluster hub to tracking head bearing.
- completeness Interface I-03 (signal) not yet defined: Controller to slew drive and actuator.
- completeness Interface I-04 (structural) not yet defined: Mast base plate to anchor rods.
- completeness Interface I-05 (electrical) not yet defined: Cell DC outputs to inverters.
- evidence CALC-01 rests on assumed values: area, psh.
- evidence CALC-02 rests on assumed values: area, psh_fixed.
- evidence CALC-03 rests on assumed values: v_design, stow_area, cd_stow, hub_height, mast_d, mast_h.
- evidence CALC-04 rests on assumed values: footing_b, dead_load, q_allow, soil_mu.
- completeness CALC-05: anchor shear (steel) has 45.6× capacity against 1.2 required — possible overdesign; consider a lighter or cheaper option (other checks may govern).
- completeness CALC-05: tension–shear interaction (≤ 1.2) has 4.13× capacity against 1 required — possible overdesign; consider a lighter or cheaper option (other checks may govern).
- evidence CALC-05 rests on assumed values: dead_load.
- evidence 16 referenced standard(s) not yet acquired or edition-checked: IEC 61215, IEC 61730 / UL 61730, UL 3703 / UL 2703, ISO 898-1, NFPA 70 (NEC) Art. 690, 694, 705, ISO 13849-1/-2, ISO 281, ISO 76, IEC 61000 series, ANSI/AISC 360, ASCE/SEI 7, ACI 318, International Building Code (as adopted locally), ASTM F1554, UL 1741, IEEE 1547.
- completeness 1 electronics item(s) to hand off to VX Design: Tracker controller with wind-stow.